Consulter and engineer’s office for energy production from renewable sources. Heat and cold care systems. Individual solutions for agriculture, local authority districts, industry and flat economy.
 
 

ANEGI GmbH Biogas, Plants and Energy Innovations



Biogas Plants - Components and Assemblies

  1. Desulphurization
  2. Fermenter
  3. Re-Fermenter
  4. Fermenting Rest Storage Unit
  5. Biogas Heating Power Unit
  6. Substratum Supply


Desulphurization as a Trickle-Bed-Reactor Systemback

  • External Desulphurization
  • Exact pH-value regulation is possible.
  • A better heat conduction for the microbiology is given by isolation of the round container.
  • The optimum reaction to seasonal variations with a steady decomposition behaviour is guaranteed.
  • All process parametres are controlled, regulated and monitored constantly. Short-term reacting to changes of the working conditions is possible.
  • Low operating expenses.
  • Low maintenance requirements.


Fermenter with Integrated Gasholderback

  • Ferro-concrete base plate from WU-concrete according to WHG and ground survey report.
  • Ferro-concrete containers from WU-precast concrete part with concrete according to WHG to max. 7.00 m above the earth.
  • Water protection by locking foil (drainage road) with a circular drainage pipeline and controlling shafts.
  • Inspectiondoors from high-grade steel by entrance height.
  • Multistage high-grade steel heating in on wall assembly.
  • Foil roof as a double membrane with central prop (external foil serves as a UV protection and weather protection, the internal foil serves as a gasholder).
  • The lead-throughs of the walls, bottom and roof are finished absolutely gasproofed as system elements.
  • If geographically possibly, overfalls are arranged in the containers.
  • Two electronically controlled sloping stirring devices and one electronically controlled submerged engine stirring devices.
  • Electronically controlled screw conveyor to insert the substratmixture
  • Gasproofed sealing with admitted multilayered coating.
  • Sensors for: temperature, pH-value, gas content, gas amounts.
  • Computer-supervised operating control with response times <1 hour.
  • Remote controlled system’s technology. (Pumps, conveyors, stirring devices etc.)


Re-Fermenter with Integrated Gasholder.back

  • Ferro-concrete base plate from WU-concrete according to WHG and ground survey report.
  • Ferro-concrete containers from WU-precast concrete part with concrete according to WHG to max. 7.00 m above the earth.
  • Water protection by locking foil (drainage road) with a circular drainage pipeline and controlling shafts.
  • Inspectiondoors from high-grade steel by entrance height.
  • Multistage high-grade steel heating in on wall assembly.
  • Foil roof as a double membrane with central prop (external foil serves as a UV protection and weather protection, the internal foil serves as a gasholder).
  • The lead-throughs of the walls, bottom and roof are finished absolutely gasproofed as system elements.
  • If geographically possibly, overfalls are arranged in the containers.
  • Two electronically controlled submerged engine stirring devices.
  • Gasproofed sealing with admitted multilayered coating.
  • Sensors for: temperature, pH-value, gas content, gas amounts.
  • Computer-supervised operating control with response times <1 hour.
  • Remote controlled system’s technology. (Pumps, stirring devices etc.)

Fermenting Rest Storage Unitback

  • If already storage containers exist, they are taken over in the investment draught.
  • Ferro-concrete base plate from WU-concrete according to WHG and ground survey report.
  • Ferro-concrete containers from WU-precast concrete part with concrete according to WHG to max. 7.00 m above the earth.
  • Inspectiondoors from high-grade steel by entrance height.
  • Foil roof as a swimming tarpaulin.
  • Seperation of the dry substances with next pelletizing of the biofertilizer.


Biogas Heating Power Unitback

  • Standardized heating power units in module constructions.
  • The container modules ready with connections are put up on construction-sided strip foundations, and are conncted with the construction-sided inducements and disposal pipelines. The Units are Remote controlled.
  • All emission limit values known up to now are kept.


Substratum Supplyback

  • Self-mixing solids starage container from steel (allows optimised substrate mixtures) founded on ferro-concrete base plate of WU concrete according to WHG and ground survey report .
  • Input controlling with load cells and screw conveyors.
  • Concrete container as a liquid material storage with ferro-concrete base plate from WU-concrete according to WHG and ground survey report, ferro-concrete container from WU-to concrete finished parts according to WHG to max. 2.00 m above the earth, ferro-concrete lid from WU-concrete according to statics with openings for a submerged engine stirring device, a submerged edge stirring device and input opening adapted for wheel loaders.
  • Water protection by locking foil (drainage road) with a circular drainage pipeline  and controlling shafts.
  • Input controlling about volume control and pumping technology.
  • Computer-supervised operating control with response times <1 hour.
  • Remote controlled system’s technology. (Pumps, stirring devices etc.)