Biogas Plants - Components and Assemblies
- Desulphurization
- Fermenter
- Re-Fermenter
- Fermenting Rest Storage Unit
- Biogas Heating Power Unit
- Substratum Supply
Desulphurization as a Trickle-Bed-Reactor System![]()
- External Desulphurization
- Exact pH-value regulation is possible.
- A better heat conduction for the microbiology is given by isolation of the round container.
- The optimum reaction to seasonal variations with a steady decomposition behaviour is guaranteed.
- All process parametres are controlled, regulated and monitored constantly. Short-term reacting to changes of the working conditions is possible.
- Low operating expenses.
- Low maintenance requirements.
Fermenter with Integrated Gasholder![]()
- Ferro-concrete base plate from WU-concrete according to WHG and ground survey report.
- Ferro-concrete containers from WU-precast concrete part with concrete according to WHG to max. 7.00 m above the earth.
- Water protection by locking foil (drainage road) with a circular drainage pipeline and controlling shafts.
- Inspectiondoors from high-grade steel by entrance height.
- Multistage high-grade steel heating in on wall assembly.
- Foil roof as a double membrane with central prop (external foil serves as a UV protection and weather protection, the internal foil serves as a gasholder).
- The lead-throughs of the walls, bottom and roof are finished absolutely gasproofed as system elements.
- If geographically possibly, overfalls are arranged in the containers.
- Two electronically controlled sloping stirring devices and one electronically controlled submerged engine stirring devices.
- Electronically controlled screw conveyor to insert the substratmixture
- Gasproofed sealing with admitted multilayered coating.
- Sensors for: temperature, pH-value, gas content, gas amounts.
- Computer-supervised operating control with response times <1 hour.
- Remote controlled system’s technology. (Pumps, conveyors, stirring devices etc.)
Re-Fermenter with Integrated Gasholder.![]()
- Ferro-concrete base plate from WU-concrete according to WHG and ground survey report.
- Ferro-concrete containers from WU-precast concrete part with concrete according to WHG to max. 7.00 m above the earth.
- Water protection by locking foil (drainage road) with a circular drainage pipeline and controlling shafts.
- Inspectiondoors from high-grade steel by entrance height.
- Multistage high-grade steel heating in on wall assembly.
- Foil roof as a double membrane with central prop (external foil serves as a UV protection and weather protection, the internal foil serves as a gasholder).
- The lead-throughs of the walls, bottom and roof are finished absolutely gasproofed as system elements.
- If geographically possibly, overfalls are arranged in the containers.
- Two electronically controlled submerged engine stirring devices.
- Gasproofed sealing with admitted multilayered coating.
- Sensors for: temperature, pH-value, gas content, gas amounts.
- Computer-supervised operating control with response times <1 hour.
- Remote controlled system’s technology. (Pumps, stirring devices etc.)
- If already storage containers exist, they are taken over in the investment draught.
- Ferro-concrete base plate from WU-concrete according to WHG and ground survey report.
- Ferro-concrete containers from WU-precast concrete part with concrete according to WHG to max. 7.00 m above the earth.
- Inspectiondoors from high-grade steel by entrance height.
- Foil roof as a swimming tarpaulin.
- Seperation of the dry substances with next pelletizing of the biofertilizer.
- Standardized heating power units in module constructions.
- The container modules ready with connections are put up on construction-sided strip foundations, and are conncted with the construction-sided inducements and disposal pipelines. The Units are Remote controlled.
- All emission limit values known up to now are kept.
- Self-mixing solids starage container from steel (allows optimised substrate mixtures) founded on ferro-concrete base plate of WU concrete according to WHG and ground survey report .
- Input controlling with load cells and screw conveyors.
- Concrete container as a liquid material storage with ferro-concrete base plate from WU-concrete according to WHG and ground survey report, ferro-concrete container from WU-to concrete finished parts according to WHG to max. 2.00 m above the earth, ferro-concrete lid from WU-concrete according to statics with openings for a submerged engine stirring device, a submerged edge stirring device and input opening adapted for wheel loaders.
- Water protection by locking foil (drainage road) with a circular drainage pipeline and controlling shafts.
- Input controlling about volume control and pumping technology.
- Computer-supervised operating control with response times <1 hour.
- Remote controlled system’s technology. (Pumps, stirring devices etc.)